Japan Donates Solar Power Worth $9.7 million To Boast Electricity In Nigeria

0


The Government of Japan, through its agency, Japan International Cooperation Agency (JICA), has donated solar power worth $9.7 million to the Federal Government to boost electricity in the country. 

The Ambassador of Japan to Nigeria, Mr Sadanobu Kusaoke, made this known in Abuja on Tuesday during the inauguration of the project. Kusaoke stated that Japan considered the power sector as one of the most important areas to enhance Nigeria`s socio-economic development.

 “Since from 1970s, Japan has helped to finance power sector to increase the capacity of power in Kainji dam hydro power station. “This is the 10th project of power sector by the Japan`s Government since then and this will not be our last. 
“ He said the project which entailed the introduction of clean energy by solar electricity was donated by the government of Japan to boost power and water supply at Usman Dam Water Treatment Plant. “The project is being executed with grant assistance worth Nine Hundred and Eighty Million Japanese YEN (980,000,000 JPY) (equivalent to approximately 9.7 million USD) through JICA, ” he said. 

 He commended the designer of the project, Toyota Tsusho Corporation, for its design, management and the completion of the project on schedule.

Kusaoke, who explained that the project was capable of generating 1,496MWH, added that this would result in reduction of N31.5 million per year for payment of the electricity bill. 

Earlier, Mr Hirotaka Nakamura, Chief Representative of JICA, Nigeria office, said improving core infrastructure including power sector in Nigeria was one of the priority areas of the agency in Nigeria.

Nakamura said developing alternative energy resources such as solar, wind and hydropower will boost electricity in the country. He explained that the project was designed to introduce a demonstration unit of solar electricity generation system with a view to increasing its economic strength on a sustainable basis. According to the JICA official, with the Japanese assistance, about 1.2 mw of grid connected solar generation will be gained at Usman Dam Water Treatment Plant to supplement electricity supply from the national grid.


“Following successful tests on the installed solar system, the first phase of the project with generation capacity of 975kwp is being commissioned today. “The second phase will bring additional 207kwp generation to this system hopefully in January 2017. ”
Nakamura further stated that the project would contribute to the improvement of quality water supply in the Federal Capital Territory. He, therefore, appealed to the FCT administration through its water board to handle the project with care and also provide sufficient funds to maintain the generation system.

Leave A Reply

Your email address will not be published.