FG To Reopen Third Mainland Bridge Midnight

0

Third Mainland BridgeFederal Controller of Works in Lagos State, Mr Olukayode Popoola, has on Sunday said the total shutdown of Third Mainland Bridge would be lifted at midnight, 24 hours ahead of scheduled time.

Popoola told News Agency of Nigeria in Lagos State that the total shutdown had to be lifted because the contractor was able to fast-track the delicate task they needed to execute.

Read Also: FG To Shut Third Mainland Bridge For Six Months

He said that the initially scheduled 72 hours timeframe was achieved within 48 hours, hence the reopening to traffic 24 hours ahead of schedule.

Popoola expressed;

We have completed the casting of the three number expansion joints on Third Mainland bridge. Therefore, the bridge shall be opened at 12:00 midnight Sunday 27th December, and no longer Monday 28th December. That is 48 hours and no more 72 hours.

It would be recalled that the controller on Tuesday, December 22 announced a 72 hours total shutdown of the bridge with effect from midnight on Saturday to midnight Tuesday.

Read Also: FG To Close Third Mainland Bridge, Lagos-Ibadan Expressway After Christmas

The shutdown was to stop vibrations caused by the movement of vehicles for contractors to cast concrete on additional three expansion joints in the ongoing rehabilitation of the bridge.

NAN reports that Third Mainland Bridge which was going through a series of repairs had to be partially shut on July 24 for another round of rehabilitation works.

The repair that was expected to last six months was extended by one month due to the recent #EndSARS protests in Lagos State, thereby extending the completion date from January 2021 to February.

The construction was initially divided into two phases of three months on each carriageway, starting with Oworonsoki bound carriageway whose completion dragged to four months.

Traffic was partially diverted on a stretch of 3.5km where construction is ongoing between Adeniji Adele Ramp and Ebute Metta, while different time belts were allotted for traffic diversions on the bridge.

The 11.8km bridge is the longest of three bridges connecting Lagos Island to the Mainland.

The bridge starts from Oworonshoki, which is linked to the Apapa-Oshodi Expressway and the Lagos-Ibadan Expressway and ends at the Adeniji Adele Interchange on Lagos Island.